INA refinery - Sisak, Croatia

Investor: Galil Engineering ltd. Israel
Area: 6 Month/s
Construction window: 5 Million Euros

Plant was carried out at 360 AB pilots depth 20-26 m, performed within 60 days. In the basic rate it was built 1020 anchor bolts with an accuracy of  +/- 2 mm for mounting the reactor (height 65 m) and other equipment.