ROCKWOOL - Potpićani, Istra, Croatia
Investor: | ||||||||
The biggest green field investition in Croatia. There are five main, large objects and ten smaller ones. Total steel construction quantity is 3.000 t. Building of that steel construction took 5 months. 20.000 m3 of concrete and 3.000 t of reinforcement was used. The project was completed to full functionality, with all construction, trade and installation works, and landscaping. latest news Copyright © 2018, Zagorje - Tehnobeton d.d. |