ROCKWOOL - Potpićani, Istra, Croatia
Investor:  
Investor: Rockwool International / Rockwool Adriatic Company
Area: 40000 m2
Construction window: 11 Month/s
Works value: 37 Million Euros

The biggest green field investition in Croatia. There are five main, large objects and ten smaller ones. Total steel construction quantity is 3.000 t. Building of that steel construction took 5 months. 20.000 m3 of concrete and 3.000 t of reinforcement was used. The project was completed to full functionality, with all construction, trade and installation works, and landscaping.

Web development: marker.hr